CodeDescriptionUnitRate
32.01Providing internal cement plaster 6 mm thick in a single coat in cement mortar 1:4 without neeru finish to concrete surface in all positions including scaffolding and curing etc. complete.sqm₹ 203
32.02Providing internal cement plaster 6 mm thick in a single coat in cement mortar 1:3 without neeru finish to concrete surface in all positions including scaffolding and curing etc. complete.sqm₹ 209
32.03Providing internal cement plaster 12mm thick in single coat in cement mortar 1:5 without neeru finish to concrete or brick surfaces, in all positions including scaffolding and curing etc. complete.sqm₹ 271
32.04Providing internal cement plaster 12mm thick in single coat in cement mortar 1:4 without neeru finish to concrete or brick surfaces, in all positions including scaffolding and curing etc. complete.sqm₹ 278
32.05Providing internal cement plaster 12mm thick in single coat in cement mortar 1:3 without neeru finish toconcrete orbrick surfaces, in allposition includingscaffolding and curing etc. complete.sqm₹ 289
32.06Providing internal cement plaster 20mm thick in Single coats in cement mortar 1:5 without neeru finish, to concrete, brick surface, in all positions including scaffolding and curing etc. completesqm₹ 375
32.07Providing internal cement plaster 20mm thick in Single coats in cement mortar 1:4 without neeru finish, to concrete, brick surface, in all positions including scaffolding and curing etc.complete.sqm₹ 382
32.08Providing internal cement plaster 20mm. thick in Single coats in cement mortar 1:3 without neeru finish, to concrete, brick surface, in all positions including scaffolding and curing etc. complete.sqm₹ 393
32.11Providing sand faced plaster externallyin cement mortar using approved screenedsand, in all positions including base coat of 15 mm thick in cement mortar 1:4 using waterproofing compound at 1Kilogramper cement bag curing the same for not less than 2 days and keeping the surface of the base coat rough to receive the sand faced treatment 6 to 8 mm thick in cement mortar 1:4 finishing the surface by taking out grains and curing for fourteen days scaffolding etc.complete.sqm₹ 639
32.12Providing rough cast cement plaster externally in two coats to concrete, brick or stone masonry surfaces in all positions with base coat of 12 to 15 mm thick in C.M. 1:4 and rough cast treatment 12mm thick in proportion 1:1 1/2:3 including scaffolding and fourteen days curing complete.sqm₹ 563
32.13Providing rough cast cement plaster externally in two coats with coloured cement finish to concrete/ brick/ stone masonry surfaces in all positions with base coat 12 to 15 mm. thick in C.M. 1:4 using gray cement and rough cast treatment 12 mm thick in proportion of 1:1 1/2:3 using colour pigment including scaffolding and fourteen days curing etc. complete.sqm₹ 574
32.15Providing neeru finish to plastered surfaces in all positions including scaffolding and curing etc. complete.sqm₹ 65
32.16Providing flush grooved pointing with cement mortar 1:3 for brick work including scaffolding and curing etc. complete.sqm₹ 173
32.17Providing flush grooved pointing with cement mortar 1:3 for stone masonry work including scaffolding and curing etc. complete.sqm₹ 182
32.18Providing tuck pointing with cement mortar 1:3 for stone/Brick masonry including scaffolding and curing etc. complete.sqm₹ 179
32.19Providing weathered pointing with cement mortar 1:3 for stone/ Brick masonary including scaffolding and curing etc. complete.sqm₹ 179
32.20Providing vee pointing with cement mortar 1:3 for stone / Brick masonry including scaffolding and curing etc. completesqm₹ 173
32.21Providing fine cement finish 1.5 mm thick over green plaster surface including scaffolding curing etc. complete.sqm₹ 72
32.22Labour charges for providing groove in external plaster having width and spaced as directed by engineer incharge etc. complete.rmt₹ 49
32.23Providing patti/ band 75mm wide on plastered surface 12 mm to 15 mm thick in C.M. 1:3 line and level including neat finishing scaffolding curing etc. complete.rmt₹ 52
32.24Providing patti/ band 100mm wide on plastered surface 12 mm to 15 mm thick in C.M. 1:3 line and level including neat finishing scaffolding curing etc. complete.rmt₹ 67
32.25Providing patti/ band 150mm wide on plastered surface 12 mm to 15 mm thick in C.M. 1:3 line and level including neat finishing scaffolding curing etc. complete.rmt₹ 81
32.26Providing and fixing chicken mesh of 22 gauge, with about 30 cm. width at the junction of R.C.C members and brick work, of approved quality including fixing mesh in position bynecessary drilling in concrete /B.B.masonry and or tying by binding wire etc. complete.rmt₹ 57
32.27Providing and applying plaster with plaster of paris in 6mm thickness to previously plaster surface in all position including preparing the surface scaffolding etc. complete.sqm₹ 144
32.28Providing and applying spray plaster made with finely graded marble and quartz in 2 mm thickness in two coats using putty knife or trowel to newly plaster fairly even surface after minimum 30 days gap in all position including finishing the surface using zero One Number sand paper or fine emry paper gently level the area by moving paper in round circles removing the dust and clean the surface with dry cloth and scaffolding including all materials and labour etc. complete.sqm₹ 263
32.29Providing and applying laying Aggregate plaster in granite / marble stones, as decorative finish to give granite / marble like appearance to concrete, brick or block surfaces in all position including preparation of surface smoothly, evenly by racking of joints in case of Brick or block work including backing layer of 12 mm thick with cement mortar 1:3 with 2% integral cement water proofing compound, roughening for wall keying hardening and drying the surface for a minimum five days gaps including second coat of cement lime mortar into a proportion 1:4 preparing the surface for three coat of marble finish plaster giving a thin coat of white cement and two parts of course calcite powder, applying the mortar with steel float on the surface in proper evenness applying at coat of white cement and lime to set a smooth finish then applying a thin coat of slurry made of white cement and black oxide colour in required proportion by the steel float to get black streaks on the surface and curing the surface for two days including all materials and labour etc. complete.sqm₹ 2,556
32.30Providing and applying plaster / wall punning with plaster of paris ( with plaster of paris material) in 10 to 13 millimeter thickness to previouslyplastered surface / or on newly brick surface ( Excluding rough cast plaster) in all position including preparing and Finishing the surface scaffolding etc.complete.sqm₹ 572
32.31Providing and applying gypsum plaster ( with Gypsum material) with finishing with gypsum material in 10 to 13 millimeter thickness to previously plastered surface / or on newlybricksurface(Excludingroughcast plaster)inallposition includingpreparing and Finishing the surface scaffolding etc.complete.sqm₹ 765
32.32Providing and applying Texture plaster with finishing with texture material of approved make in 3 to 4 millimeter thickness on previously plastered surface, including Plaster Groove 6mm thickness or Tape Grooves 35 to 45 mm thickness or as required, in all position including preparing the surface, scaffolding etc. complete.sqm₹ 628
32.33Removing the existing cement plaster of any thickness without causing dust nuisance and stacking the debris upto a distance of 50 metres or spreading in the compound and cleaning the site etc. complete.sqm₹ 52
32.34Providing and applying Two coats of wall care Putty on plastered surface and Ceiling and Walls to prepare surface even and smooth of approved make, etc complete.sqm₹ 90
32.36Providing cement patta/ bandof2.50cmwidthoneithersideofedgesofplasterfor doors and windows including scaffolding,finishing, curing etc. complete.sqm₹ 40
32.37Providing groove to required size at specified location as directed byEngineer,at junction of brick masonry wall and R.C.C beams or Column, at junction of composite masonry, including scaffolding, finishing, curing etc. complete.rmt₹ 40
Make the estimate with these rates. BESTimate fills the description, unit and rate when you pick the item code — Measurement, Abstract and Summary in Excel.Try BESTimate →

Source: State Schedule of Rates 2022-23, Public Works Department, Government of Maharashtra — completed rates excluding GST. Rates are shown as published; check the official book and its correction slips before you submit an estimate. BESTimate is not issued by or affiliated with this department.

Need the full estimate, not just one item?

BESTimate makes the whole government-format estimate — Measurement, Abstract and Summary in Excel — with BMC, PWD, CPWD, MJP and CIDCO rates built in. Launching 26 November 2026 · first 99 to pre-register get 50% off for 6 months.

Pre-register free →

Made free with BESTimate by F K Consultant · estimate.fkconsultant.com/calculators · approximate figures — check against your drawings and local rates.