| Code | Description | Unit | Rate |
|---|---|---|---|
| 21.01 | Excavation for foundation in earth, soil of all types, sand, gravel and soft murum, including removing the excavated material up to a distance of 50 m. beyond the building area and stacking and spreading as directed, dewatering, preparing the bed for the foundation and necessary back filling, ramming, watering including shoring and strutting etc. complete. (Lift upto 0.00 to 1.50 m.) By Manual Means | cum | ₹ 239 |
| 21.02 | Excavation for foundation in earth, soil of all types, sand, gravel and soft murum, including removing the excavated material up to a distance of 50 m. beyond the building area and stacking and spreading as directed, dewatering, preparing the bed for the foundation and necessary back filling, ramming, watering including shoring and strutting etc. complete. (Lift upto 1.5 m.) By Mechanical Means | cum | ₹ 207 |
| 21.03 | Excavation for foundation in earth, soils of all types, sand,gravel and soft murum, including removing the excavated material upto a distance of 50 metres beyond the building area and stacking and spreading as directed, dewatering, preparing the bed for the foundation and necessary back filling, ramming, watering including shoring and strutting etc. complete. (Lift from 1.5m to 3.0m) By Manual Means | cum | ₹ 314 |
| 21.04 | Excavation for foundation in earth, soils of all types, sand,gravel and soft murum, including removing the excavated material upto a distance of 50 metres beyond the building area and stacking and spreading as directed, dewatering, preparing the bed for the foundation and necessary back filling, ramming, watering including shoring and strutting etc. complete. (Lift from 1.5m to 3.0m) By Mechanical Means | cum | ₹ 258 |
| 21.05 | Excavation for foundation in hard murumincluding removing the excavated material upto distance of 50 metres beyond the building area and stacking and spreading as directed, dewatering, preparing the bed for the foundation and necessary back filling, ramming, watering including shoring and strutting etc. complete. (Lift upto 1.50 m) By Manual Means | cum | ₹ 365 |
| 21.06 | Excavation for foundation in hard murumincluding removing the excavated material upto distance of 50 metres beyond the building area and stacking and spreading as directed, dewatering, preparing the bed for the foundation and necessary back filling, ramming, watering including shoring and strutting etc. complete. (Lift upto 1.50 m) By Mechanical Means | cum | ₹ 227 |
| 21.07 | Excavation for foundation in hard murum including removing the excavated material upto a distance of 50 metres beyond the building area and stacking and spreading as directed, dewatering, preparing the bed for the foundation and necessary back filling, ramming,watering includingshoringand strutting etc. complete. (Lift from 1.5 to 3.0m) By Manual Means | cum | ₹ 414 |
| 21.08 | Excavation forfoundation inHardmurumincludingremoving theexcavated material upto a distance of 50 metres beyond the building area and stacking and spreading as directed, dewatering, preparing the bed for the foundation and necessary back filling, ramming, watering including shoring and strutting etc. complete. (Lift from 1.5 to 3.0m.) By Mechanical Means | cum | ₹ 284 |
| 21.10 | Excavation for foundation in hard murum and boulders including removing the excavated material up to a distance 50 metres, beyond the building area and stacking and spreading as directed, dewatering, preparing the bed for the foundation and necessary back filling, ramming, watering including shoring and strutting etc. complete. (Lift upto 1.5m.) By Mechanical Means | cum | ₹ 252 |
| 21.12 | Excavation for foundation in Hard murum and boulders including removing the excavated material upto a distance of 50 metres, beyond the building area and stacking and spreading as directed, dewatering, preparing the bed for the foundation and necessary back filling, ramming, watering including shoring and strutting etc. complete. (Lift from 1.5 m to 3.0 m.) By Mechanical Means | cum | ₹ 312 |
| 21.14 | Excavation for foundation in Soft rock and old cement or lime masonry foundations including removing the excavated material upto a distance of 50 metres beyond the building area and stacking as directed, including dewatering, preparing the bed for the foundation and necessary back filling with available earth /murum, ramming, watering including shoring and strutting etc. complete (lift upto 1.5m) By Mechanical Means | cum | ₹ 429 |
| 21.16 | Excavation for foundation in Soft rock and old cement or lime masonry foundations including removing the excavated material upto a distance of 50 metres beyond the building area and stacking as directed, including dewatering, preparing the bed for the foundation and necessary back filling with available earth/murum, ramming,watering including shoring and strutting etc. complete. (Lift from 1.5m To 3.0 m.) By Mechanical Means | cum | ₹ 524 |
| 21.17 | Excavation for foundation in Hard rock by blasting including trimming and leveling the bed by chiseling where necessary and removing the excavated material and stacking it in measurable heaps within a distance of 50 metres from the building area including dewatering and back filling with available earth/murum, watering, ramming, etc. complete. (Lift upto 1.5m) By Mechanical Means | cum | ₹ 869 |
| 21.18 | Excavation for foundation in Hard-rock by blasting including trimming and leveling the bed by chiselling where necessary and removing the excavated material and stacking it in measurable heaps within a distance of 50 metres from the building area including dewatering and back filling with available earth/murum watering, ramming etc. complete. (Lift from 1.5m To 3.0 m) By Mechanical Means | cum | ₹ 1,033 |
| 21.19 | Excavation for foundation in Hard-rock by controlled blasting including trimming and leveling the bed by chiselling where necessary and removing the excavated material and stacking it in measurable heaps within a distance of 50 metres. from the building area including dewatering and back filling with available earth soil /murum watering, ramming etc. complete. (Lift upto 1.5m) By Mechanical Means | cum | ₹ 1,322 |
| 21.20 | Excavation for foundation in Hard rock by chiselling, wedging, line drilling, etc. including trimming and levelling the bed, removing the excavated material uptoa distance of 50 metres beyond the building area stacking as directed, dewatering and back filling with available earth/ murum watering, ramming etc. complete. (Lift upto 1.5 m). By Mechanical Means | cum | ₹ 1,307 |
| 21.21 | Excavation for foundation in laterite rock (soft or hard) including trimming and levelling the bed for the foundation, removing the excavated material up to a distance of 50 metres beyond the building area, stacking as directed, dewatering and back filling with available murum, watering, ramming etc. complete. (Lift upto 1.5 m.) By Mechanical Means | cum | ₹ 1,465 |
| 21.22 | Providing preconstructional antitermite treatment as per I.S. 6313 (Part-II) by treating the bottom surface and sides of excavation at the rate of 5 litres of emulsion concentrate of 1.0 percent of chlorophyrifos per square meter of surface area covering 10 years guarantee on bond paper. | sqm | ₹ 107 |
| 21.23 | Providing preconstructional antitermite treatment as per I.S. 6313 (Part-II) treatment by treating the backfill in immediate contact with foundation at the rate of 5 litres of emulsion concentrate of 1.0 percent of clorophyrifos per One Square Metre of vertical surface area covering 10 years guarantee on bond paper. | sqm | ₹ 112 |
| 21.24 | Providing preconstructional antitermite treatment as per I.S. 6313 (Part-II) bytreating the top surface of plinth filling at the rate of 5 litres of emulsion concentrate at 1.0 percent of clorophyrifos per One Square Metre of surface area covering ten years guarantee on bond paper. | sqm | ₹ 108 |
| 21.25 | Providing preconstructional antitermite treatment as per I.S. 6313 (Part-I) to the soil along the external face of building by punching holes of 1.2 of 1.5 C.M. diametre about 30 -60 cmdeep at 15 cm c/c as close to the wall as possible and to inject 0.5 percent of aldrin or clorophyrifos at the rate of 7.5 litres per hole and sealing the same with proper filling and covering 10 years guarantee on bond paper. | sqm | ₹ 176 |
| 21.26 | Providing antitermite treatment to the wooden frames of doors/windows of the existing building as per I.S. 6313 (Part-III) by drilling 6mm dia. holes at four corners on one side and four corners on other side at a downward angle of about 45 degree at the junction of wood work and masonary and injecting 150 ml. of chlorodane 5% W.C. and sealing by filling putty etc. complete covering 2 years guarantee on bond paper. | nos | ₹ 74 |
| 21.27 | Providing antitermite treatment to the joints of wooden beams/joist usedfor theroof work of the existing building as per I.S. 6313 (Part-III) by drilling 6mm dia. holes at a downward angle of about 45 degree at the junction of wood work and masonary and injecting 80 ml. of chlorodane 5% W.C. and sealing by filling putty etc. complete covering 2 years guarantee on bond paper. | nos | ₹ 57 |
| 21.28 | Providing antitermite treatment to the sides of flooring of the existing building as per I.S. 6313 (Part-III) by punching holes 6mm dia. drilled at a distance of 30cm. centre to centre and injecting one percent of chlorodane emulsion concentrate at the rate of 50 ml per hole and sealing byfilling puttyetc. complete covering 2 years guarantee on bond paper. | nos | ₹ 26 |
| 21.29 | Providing antitermite treatment around the periphery of the existing building as per I.S. 6313 (Part-III) by excavating trenches of 20cm width and exposing the sides of columns and plinth beams upto a depth of 300mm and injecting one percent of chlorodane emulsion concentrate at the rate of 2.25 litres per One Running Metre and refilling the trenches etc. complete covering 2 years guarantee on bond paper. | rmt | ₹ 67 |
| 21.30 | Providing general pest control services to the building to control the nuisance of cockroaches, lizards, pin bores and other insects etc. with 4 operations in a year and monthly check up. | sqm | ₹ 24 |
| 21.31 | Providing general pest control services to small size of inspection chamber to control the nuisance of cockroaches during the year with monthly check up. | nos | ₹ 184 |
| 21.32 | Providing general pest control services to big size of inspection chamber to control the nuisance of cockroaches during the year with monthly check up. | nos | ₹ 365 |
| 21.33 | Labour charges for removing grass, thorney shrubs, Jungli shrub, Kubabul and alike grass along roadside making the ground clean by showel and phavaras etc. complete. | sqm | ₹ 7 |
| 21.34 | Removing grass, gazer grass and disposing off out of building premises including making clean the ground by shovel and phavaras etc. complete. | sqm | ₹ 6 |
| 21.36 | Filling in plinth and floors with approved excavated material in 15cm. to 20cm. Layers including watering and compacting etc. complete. | cum | ₹ 120 |
| 21.37 | Filling in plinth and floors with contractors material/brought from outside and approved by Engineer incharge in layers of 15 cm to 20 cm including watering and compaction etc. complete. | cum | ₹ 599 |
| 21.38 | Providing dry/ trap/ granite/ quartzite/ gneiss rubble stone soling 15 cm to 20 cm thick including hand packing and compacting etc. complete. | cum | ₹ 1,382 |
| 21.39 | Providing and filling in the foundation with sand of approved quality including watering, compacting etc. complete. (To be executed with prior approval of Superintending Engineer) | cum | ₹ 2,160 |
| 21.40 | Providing soling using 80 mm size trap metal in 15 cm. layer including filling voids with Crushed sand/grit, ramming, watering etc. complete. | cum | ₹ 1,454 |
Source: State Schedule of Rates 2022-23, Public Works Department, Government of Maharashtra — completed rates excluding GST. Rates are shown as published; check the official book and its correction slips before you submit an estimate. BESTimate is not issued by or affiliated with this department.
Need the full estimate, not just one item?
BESTimate makes the whole government-format estimate — Measurement, Abstract and Summary in Excel — with BMC, PWD, CPWD, MJP and CIDCO rates built in. Launching 26 November 2026 · first 99 to pre-register get 50% off for 6 months.
Made free with BESTimate by F K Consultant · estimate.fkconsultant.com/calculators · approximate figures — check against your drawings and local rates.