| Code | Description | Unit | Rate |
|---|---|---|---|
| J1-1 | Fixed cost for 1 MLD | job | ₹ 76.44 |
| J1-2 | Add for capacity above 1 MLD upto 2 MLD | MLD | ₹ 33.86 |
| J1-3 | Cost of 2 MLD treatment plant | job | ₹ 110.3 |
| J1-4 | Add for capacity above 2 MLD upto 5 MLD | MLD | ₹ 25.63 |
| J1-5 | Cost of 5 MLD treatment plant | job | ₹ 187.19 |
| J1-6 | Add for capacity above 5 MLD | MLD | ₹ 20.07 |
| J1-7 | Cost of 10 MLD treatment plant | job | ₹ 287.53 |
| J1-1' | Upto 5 MLD | MLD | ₹ 47.22 |
| J1-2' | Cost of 5 MLD treatment plant | job | ₹ 236.1 |
| J1-3' | Add for capacity above 5 MLD upto 10 MLD | MLD | ₹ 33.89 |
| J1-4' | Cost of 10 MLD treatment plant | job | ₹ 405.54 |
| J1-5' | Add for capacity above 10 MLD upto 20 MLD | MLD | ₹ 21.66 |
| J1-6' | Cost of 20 MLD treatment plant | job | ₹ 622.15 |
| J1-7' | Add for capacity above 20 MLD upto 50 MLD | MLD | ₹ 20.07 |
| J1-8 | Cost of 50 MLD treatment plant | job | ₹ 1,224.37 |
| J1-9 | Add for capacity above 50 MLD upto 100 MLD | MLD | ₹ 16.95 |
| J1-10 | Cost of 100 MLD treatment plant | job | ₹ 2,071.64 |
| J1-11 | Add for capacity above 100 MLD | MLD | ₹ 12.35 |
| J1-1'' | 21 Cum/Hr. (0.50 MLD) | nos | ₹ 38.7 |
| J1-2'' | 34 Cum/Hr. (0.80 MLD) | nos | ₹ 47.92 |
| J1-3'' | 42 Cum/Hr. (1.00 MLD) | nos | ₹ 54.02 |
| J1-4'' | 63 Cum/Hr. (1.50 MLD) | nos | ₹ 67.67 |
| J1-5'' | 83 Cum/Hr. (2.00 MLD) | nos | ₹ 80.14 |
| J1-6'' | 125 Cum/Hr. (3.00 MLD) Note: Depending upon the capacity required for the scheme, one of the above capacities should be chosen. Sewage Treatment Plant (STP) 4A Designing (aesthetically), providing, constructing and giving satisfactory trials of modernised Sewage Treatment Plant consisting of receiving chamber, screen chamber, grit chamber, measuring flume, distribution chamber with primary and secondary treatment, etc. as detailed below, administration block of suitable size including allied units for waste disposal with all civil and mechanical works involved, etc. complete (turn key job). Primary treatment - with extended sludge drying beds Rates | nos | ₹ 102.6 |
| J1-1''' | Upto 10 MLD | ||
| J1-1'''.1 | Upto 10 MLD | MLD | ₹ 67.44 |
| J1-1'''.2 | Upto 10 MLD | MLD | ₹ 80.58 |
| J1-2''' | Cost of 10 MLD plant | ||
| J1-2'''.1 | Cost of 10 MLD plant | job | ₹ 674.38 |
| J1-2'''.2 | Cost of 10 MLD plant | job | ₹ 805.77 |
| J1-3''' | Add for capacity above 10 MLD upto 20 MLD | ||
| J1-3'''.1 | Add for capacity above 10 MLD upto 20 MLD | MLD | ₹ 58.96 |
| J1-3'''.2 | Add for capacity above 10 MLD upto 20 MLD | MLD | ₹ 70.49 |
| J1-4''' | Cost of 20 MLD plant | ||
| J1-4'''.1 | Cost of 20 MLD plant | job | ₹ 1,263.99 |
| J1-4'''.2 | Cost of 20 MLD plant | job | ₹ 1,510.67 |
| J1-5''' | Add for capacity above 20 MLD | ||
| J1-5'''.1 | Add for capacity above 20 MLD | MLD | ₹ 50.52 |
| J1-5'''.2 | Add for capacity above 20 MLD | MLD | ₹ 60.78 |
| J1-6''' | Cost of 50 MLD plant | ||
| J1-6'''.1 | Cost of 50 MLD plant | job | ₹ 2,779.46 |
| J1-6'''.2 | Cost of 50 MLD plant | job | ₹ 3,334.05 |
| J1-7'' | Add for capacity above 50 MLD | ||
| J1-7''.1 | Add for capacity above 50 MLD | MLD | ₹ 38.18 |
| J1-7''.2 | Add for capacity above 50 MLD | MLD | ₹ 45.57 |
| J1-8' | Cost of 100 MLD plant | ||
| J1-8'.1 | 4B Designing (aesthetically), providing, constructing and giving satisfactory hydraulic testing, commissioning and giving satisfactory trials of modernised Sewage Treatment Plant consisting of inlet chamber, screen chamber, detritus tanks, parshall flume, primary settling tanks, aeration tanks, secondary settling tanks, sludge sump and pump house, sludge thickener, primary digester, secondary digester, SST sump and pump house, chlorine contact tank, chlorinators, chlorinator room, sump cum blending tank, PST sludge sump cum blending tank, pump house, sludge centrifuge, gas holder, necessary piping work with required valves, gates, drains, pathways, administrative building cum laboratory, laboratory equipments, tools and plants, spare parts, etc. complete as turnkey job with all involved civil, electrical and mechanical works inclusive of following items, units as per detailed specification for civil, electrical and mechanical components with all duties and taxes, etc. complete. Inlet Chamber Designing, providing and constructing RCC (M-300) inlet chamber designed for the peak flow 2 DWF including necessary excavation in all types of strata including walkway around the periphery. Each compartment will have phosphor bronze, steel gate with extension rod, head stock, operating wheel, G.I. pipe railing, etc. The work includes providing and making necessary arrangements to connect the flow to screen chamber by approach channel as directed and as per specifications. Screen Chambers Designing, providing, constructing, testing and commissioning screen chamber designed for average DWF and maximum 2 DWF in RCC (M-300) including inlet pipe/ channel from inlet chamber, outlet pipe/ channel to detritus tank, free board of 0.50 M minimum, RCC walkway 1.2 M wide with G.I. pipe railing, RCC staircase of 1.2 M width from GL to screen chamber. Detritus Tank Designing, providing and constructing continuously grit removal type of detritus tank, mechanically operated RCC (M-300) capable of removing 100%, 0.20 mm size particle and above, having specific gravity 2.30 designed for one peak 2 DWF with suitable arrangement of separation of grit from putrescible solids including providing and making necessary arrangement of JB-1 inlet and outlet channel of required sizes as may be required to connect the flow to parshall flume, etc. complete including hydraulic testing for water tightness of the structure having minimum free board of 0.30 M washout arrangement to grit chamber and platform 1.20 M wide RCC walkway with G.I. pipe hand railing shall provided. A pit for collecting grit conveyed by conveyor shall be provided.. It should be suitable to handle the grit for carting. All arrangements shall be as per detailed specifications and as directed. Parshall Flume Designing, providing and constructing parshall flume channel in RCC (M-300) for measuring quantity of sewage received at the treatment works, max. flow of DWF and minimum flow of % DWF including providing and making necessary arrangement of approach channel as may be required to connect the flow having minimum velocity of 0.3 M per second to distribution box (DB-1). The unit shall be provided with walkway and RCC staircase having width of 1.20 M each etc. complete, including hydraulic testing for watertightness of the civil structure having free board of 0.6 M including electrically operated, flow indicating and flow integrating devices having a standby of float operated ROF meter. All arrangements as per specifications. Primary Settling Tanks with Equipments Designing, providing, constructing and hydraulic testing in RCC (M-300) watertight primary settling tanks of 1 DWF capacity with feed chamber, sludge and effluent chamber, base adequately supported, providing 1.20 wide clear peripheral and approach walkway inter connecting C.I. double flanged pipes from feed chamber of the clarifier distribution well, grouting wherever necessary, including foundation, etc. as per specifications, water depth at outer side shall be minimum 3.0 M, weir loading shall not be greater than 125 cum, DWF for average flow, bottom slope shall be 1:12. The floor of clarifier shall have 40 mm thick (min.)screed course of cement grout of mix in CM 1:2 detention period shall be 2.25 hrs. dispersion box and stiffened weir plate made of mild steel plate not less than 8 mm thick, anticorrosive epoxy paint on both faces shall be provided. Minimum free board of 0.50 M be provided. It includes inlet pipe from distribution chamber, central shaft, inlet baffle, outlet chamber, scum remover, skimming device, scum chamber, connecting channel from PST, outlet chamber to DB-2 as per detailed specifications. Aeration Tank (AT) Designing, providing and constructing in RCC mix (M- 300) aeration tank in compartments to handle combined flow of 1 DWF incoming flow and recirculation flow including construction of inlet, outlet and distribution chamber DB-3 and providing 1.20 m wide clear peripheral approach walkways, expansion joints wherever necessary, including foundation, etc. as per specifications. Peak factor shall be 2, F/M ratio shall be 0.40, low speed aerator speed between 20 to 100 RPM, recirculation flow @50% and free board 0.60 m depth, (SWD) 3.50 M minimum, D.O. level at A.T. 2 mg/lit, MLVSS concentration shall be 2500 mg/lit and MLVSS concentration shall be 2000 mg/lit, HRT shall be 4 to hours and STR 6-8 days. It should have compartments for washing, oxygen transfer capacity of mechanical aerator shall not be less than 1.5 kg/KWH, BOD of effluent 20 mg/lit with input aerator 0.15 to 0.30 KWH/1000 cum of aeration tank. All related works shall be as per detailed specifications. Secondary Settling Tanks with Equipments Designing, providing and constructing in RCC (M-300) water tight secondary settling tank having detention period 2 hours and SWD shall be 4.20 M. The effluent BOD & SS from the secondary clarifier shall not be more than 20 Mg/lit and 30 Mg/lit respectively. It should be hydraulically tested, bottom floor slope of 1:12 and free board of 0.60 M minimum. Dispersion box shall be made of mild steel plate not less than 8 mm thick with anticorrosive epoxy paint from both faces and well stiffened. The sewage admitted at the centre flowing upward and outward towards periphery be slowly and continuously collected towards a convenient discharge point near centre by a rotating wheel arm. The clarifier will be completed with end drive half rotating bridge, structural steel rake, overflow weir, walkway diffuser, over load alarms, having push buttons, starters for the clarifier, walkway and the suitable sludge withdrawing arrangement with flush valve capable of withdrawing moisture content not more than 97% to 98% slopping floor shall have 40 mm thickness (minimum), screed course of cement grout of mix 1 cement: 2 sand, rotating sludge scrapper mechanism fitted with squeezes including providing and making necessary arrangement to connect the flow to outlet chamber (DB- 4) then the gravity mains for final disposal and as per detailed specifications and obligatory provision. All other arrangements shall be as per detailed specifications. Sludge Thickener with Equipments Designing, providing and constructing watertight sludge thickener (gravity type) including foundation in RCC (M300) with inlet and outlet chamber influent well, inlet and outlet pipes, with sludge pit and sludge removal arrangement, grouting wherever necessary with walkway all around of 1.20 M width G.I. pipe railing interconnecting CI pipes all complete as per specifications, detention time 24 hours. SWD shall be 4.25 metre with necessary fixed bridge scraper arrangement as per detailed specifications and necessary inlet and outlet arrangement. All other arrangement as per detailed specifications. Primary Digester with Mixer Equipment (Fixed Cover) Designing, providing and constructing unit of watertight and gastight primary digester suitable for 1 DWF plant and complete with pipe gallery, building, staircase for access from dome of digester into inside staircase, walkways at springing levels, etc. walls and base slab being in RCC (M-300), domes in structural concrete including providing burners and civil works for gas collection, grouting wherever necessary, etc. complete as per specifications. It should be designed for min 9°C and max. 45°C and minimum detention time of 30 days, water depth shall not be more than 8.5 M, free board shall be 0.6 M with inlet and outlet arrangement of C.I. flanged pipes including giving hydraulic testing and airtightness testing. The item includes providing works for collecting gas and gas burner as per specifications. Secondary Digester with Equipment (Fixed Cover) Designing, providing and constructing including foundation unit of watertight and gastight secondary digester to deal with 1 DWF complete with pipe gallery, building, staircase for access from dome of digester into inside, staircase to walkways at springing levels, etc. Walls and base slab and domes being in RCC M-300, providing arrangement for digested sludge from digesters centrifuge, providing burners and civil works for gas collection grouting wherever necessary, etc. complete as per specifications and obligatory provision. All other arrangements as per detailed specifications. S.S.T. Sump and Pump House with Recirculation Pumps and Sludge Pumps to Digester Designing, providing and constructing sump and pump house of requisite capacity with ceiling height not less than 6 M, sludge stream for recirculation to aeration tank and excess sludge SCBT, including C.I. piping to carry this flow to sump as per detailed specification and as directed by Engineer-in-charge. Chlorine Contact Tank Designing, providing and constructing chlorine contact chamber of adequate capacity to deal with 1 DWF average flow. The chlorine contact tank should be of 30 minutes capacity during average flow to achieve 99.99% coliform reduction. Chlorine dose shall be maintained as per standard provisions including designing, providing and constructing water supply arrangement for chlorination including providing dewatering and bypass arrangements, jointing to final effluent main and outlet weir, etc. complete. The effluent quality should match with the standards laid down by Maharashtra Water Pollution Control Board and as per the obligatory provisions and detailed specifications and as directed by Engineer-in- charge. Chlorinator and Chlorinator Room / Tonner Room Designing, providing and constructing chlorinators, vacuum type 2 nos. each having capacity of 10 Kg/hr as per obligatory provisions and detailed specifications with necessary provision of chlorinator room having floor area not less than 30 sqm including automatic residual chlorine controller with actuator and residual chlorine analyser including cost of chlorine cylinder, piping, valves, measuring and controlling equipments, safety devices, lifting equipments, etc. complete as per I.S.-10553 (Part II) 1982. The tonner room should have 3 MT capacity crane for loading and unloading facility. Tonner storage should distinctly isolated and should be for minimum 10 tonners space and arrangements as per gas laws 1981 and factory act shall be provided and all other matching amenities be provided, 5 MT gantry shall be provided for full length of tonner room at 6 M height from floor level, with outlet chamber and treated effluent outlet channel, etc. complete as per detailed specifications. Sump cum Blending Tank (SCBT) Designing, providing and constructing sump cum blending tank of appropriate size and detention time with free board of 0.60 M. The slope of floor 1:4 with suction pit at the centre as per detailed specifications and obligatory requirements. P.S.T. Sump cum Blending Tank, Pump House with Recirculation Pumps Designing, providing and constructing pump house of appropriate size with pumps, ceiling height minimum 6 M over the circular sump for discharging the sludge to thickener and recycling of flow for blending with C.I. piping, etc. complete as per detailed specifications. Sludge Centrifuge Room with Centrifuges Designing, providing, constructing and installing including foundation, etc. sludge centrifuge to handle the sludge flow of one day in one hour per unit with sludge dewatering unit, drain, etc. complete as per specifications, sludge centrifuge with all necessary arrangements as per detailed specifications mentioned in Volume-II and Volume-III of tender and obligatory provisions, be provided with satisfactory functioning. Gas Holder Designing, providing and constructing gas holder having gas collection system, gas flow meter and gas burner with floating dome arrangement and storage time 6 hrs. to be constructed in M-300 having appropriate diameter as per detailed specifications and obligatory provisions. The floating dome shall be of 8 mm thick M.S. plate minimum and shall be provided with two coats of anti- corrosive epoxy coating from both faces. Outfall Sewer Designing, providing and constructing appropriate outfall sewer of RCC NP-2 pipe to discharge treated effluent, untreated effluent from outlet chamber (after basin / chlorination tank) to the local nalla at a point shown on the drawing including necessary chambers inspection / cleaning including necessary excavation, dewatering, refilling, concrete encasing/ bedding concrete steps to reach the nalla bed level, pitching and energy dissipation chamber in the nalla portion, etc. complete upto 50 M length RCC NP-2 pipeline and including all above items. Piping Work in CI 'LA' class including Sluice Valve, Reflux Valve, M.S. Gate Providing, laying and jointing pipes other than those already included in the above items for interconnection bypass drains, etc. of all units including adequate numbers of manhole chambers. The item includes excavations, refilling and hydraulic testing of pipes, valves, gates, accessories and cost of jointing materials. The item includes required channels with gates for interconnection of units, bypass drains, etc. all units and as directed, etc. complete as per detailed specifications. Administrative Building cum Laboratory (G+1) Designing, providing and constructing administrative building, office cum labo rat o ry including stores. This shall be a building having appropriate carpet area at ground floor and at first floor complete as per specifications including necessary excavation, foundation in RCC M-200 framed structure, BB masonry (IInd class in CM 1:6) 20 mm cement plaster in CM 1:3 inside and outside painting, aluminium door and window with glass panels, mosaic tile flooring and skirting and all other allied items, fixtures, fastening electrification arrangements, water supply arrangement, etc. complete. The building will have laboratory on upper floor of administrative building and should be so centralised that it should not be attached with any unit but should have complete control of every unit as per laboratory equipment, beautification, telephone and intercom arrangement and wireless system. Primary and secondary treatment-with digesters, sludge drying beds, etc. complete. Rates | job | ₹ 4,688.25 |
| J1-8'.2 | Integrated Wetland Technology (IWT) BASED | job | ₹ 5,612.42 |
| J1-5'''' | SEWAGE TREATMENT PLANT Designing, providing, constructing, hydraulic testing, commissioning and giving satisfactory trials of Integrated Wetland Technology (IWT) based Sewage Treatment Plant (STP) consisting of Screen chamber, Oil &Grease trap, RCC Primary treatment tanks (including manholes, vent pipes and graded gravel media) and RCC Secondary treatment tanks (SBBR) (including gravel media, PVC sheets, wetland plants, plastic mesh, etc. required.) tank, RCC intermediate and treated water tank, sludge recirculation pump and pipe network, room for tertiary treatment unit, E&M works for tertiary treatment including associated piping work, internal pathways, wire fencing, etc. complete as turnkey job with all involved civil, electrical and mechanical works inclusive of following items, units as per detailed specifications for civil, electrical and mechanical components with all duties and taxes, etc. complete as directed by Engineer-In-charge. Allied structure shall constructed as per the provision in appropriate and relevant standards and design guidelines of respective authorities. RCC and civil works will be as directed by Engineer-in-charge. Sewage Treatment Plant (STP) to designed to treat the row water sewage with the characteristics in table number "A" to produce the treated sewage with characteristics as mentioned in table number "B" A Raw Sewage Characteristics Temperature - Ambient pH - 5.5-9.0 BOD - 300 mg/L 5 COD - 600 mg/L TSS -500 mg/L Total N: 50 mg/L Total P: 15 mg/L Faecal Coliform (MPN): 10^6- 10^7 B Treated Water Characteristics Temperature - Ambient pH - 6.5-8.0 BOD < 10 mg/L 5 COD - 40 mg/L TSS < 20 mg/L Total N < 5 mg/L Total P <1 mg/L Faecal Coliform (MPN) < 10 mg/lt Note: If raw sewage characteristics observed as per test are more critical than the mentioned in description (Table A) same shall be used for the design of Sewage Treatment Plant (STP), otherwise row sewage characteristics mentioned ( Table A)shall be used. II FOLLOWING COMPONENTS ARE INCLUDED 1. SCREEN CHAMBER: Screening is a unit operation that separates large floating materials in and/or on water found in different and/or on water (found in different sizes) from water and from entering wastewater treatment facilities and mains. The unit known as a screen chamber 2. Oil and Grease Trap Designing, providing and constructing manual type Oil &Grease removal mechanism in RCC (M-300) capable removing grease, oil and scum including providing and making necessary arrangements. Removal will be done manually and stored in a tank for defined period after which it will be disposed to appropriate disposal facility. Inlet and outlet channels of required sizes as make be required to connect the flow to connecting unit, etc. complete including hydraulic testing for water tightness of structure having adequate Free Board, and platform. All arrangements shall be as detailed specifications and as directed by Engineering in Charge. 3. Primary Treatment Tank Designing, providing, constructing and hydraulic testing in RCC (M-300) watertight underground primary treatment tanks (including PSRT, SABR, BSF). Designs per the drawings given by IWT technology provider. Design will consider the average flow, the 2 DWF and the peak flow. Tank will be covered and PVC vent pipes having sand and activated carbon (as per details and design provided by technology provider) will be installed to prevent odour. 0.5% of horizontal slope is provided in the tank for the collection of sludge. Minimum free board of 0.3m is provided. It includes providing all necessary items such as gravel media, piping, valves, joints, launder, baffling, etc. as shown drawings & additional items will be as directed by Engineering in Charge. 4.Static Bed Biofilm Reactor (SBBR) Designing, providing, constructing and hydraulic testing in RCC (M-300) watertight underground secondary treatment tanks (SBBR). 0.5% of horizontal slope is provided in the tank for the collection and recirculation of sludge. Designs as per the drawings given by IWT technology provider. Design will consider the average flow, the 2 DWF and the peak flow. Wetland plants will be planted on gravel media ( as per designed by IWT technology provider). In the open recirculation sections a combination of Bottom screen, MS mesh, PVC sheet, plastic mesh will be provided to support Wetland plants. Minimum free board of 0.3m is provided. It includes providing all necessary items such as gravel media, piping, valves, joints, launder, baffling, structural steel work, bottom screens, grill work, pvc sheet, plastic mesh, wetland plants etc. as shown in drawings and additional items will be as directed by Engineering in Charge. 5. Intermediate and Treated Water Tank Designing, providing, constructing and hydraulic testing in RCC (M-300) watertight underground tank acting as feed tank for tertiary treatment avoiding backflows. Designs as per the drawings given by IWT technology provider. Design will consider the average flow, the 2 DWF and the peak flow. Tank will be covered. It includes providing all necessary items such as piping, valves, joints etc. as shown in drawings & additional items will be as directed by Engineering in Charge. 6. Tertiary Treatment Unit Designing, providing, installing and hydraulic testing of feed pump, activated carbon filter vessel with required sand and required activated carbon quantities, hypo dosing tank, dosing pump, necessary piping, pumps, joints, electrical cables, connections etc. complete. It also includes trail and run of tertiary treatment unit. After dosing contact time of 30 min allows 99.99% reduction of outstanding fecal coliform. Chlorine dosage will be as per standard requirement of 5- 10ppm. to match effluent quality as mentioned in table number "B". The Unit as per designed and approved technology provider. 7. Treated Water Outfalls Designing, providing, constructing appropriate outfall sewer of RCC NP Class -III pipe to discharge treated effluent, untreated effluent from bypass chambers to the local Nallah at the point shown on the drawing including necessary chambers for inspection and cleaning including excavation, dewatering, refilling, concrete, encasing / bedding concrete to the local Nallah at the point shown on the drawing including necessary chambers for inspection and cleaning including excavation, dewatering, refilling, concrete, encasing / bedding concrete 8. Block Diagram Integrated Wetland Technology (IWT) III PRICE SCHEDULE Capacity of the Plant in MLD Area Requirement in Sqm | ||
| J1-5''''.1 | 0.050 MLD 110 | job | ₹ 2,911,110 |
| J1-5''''.2 | Add capacity above 0.050 MLD to 0.100 MLD | litre | ₹ 35.85 |
| J1-5''''.3 | 0.10 MLD 250 | job | ₹ 4,703,666 |
| J1-5''''.4 | Add capacity above 0.10 MLD to 0.25 MLD | litre | ₹ 32.26 |
| J1-5''''.5 | 0.25 MLD 630 | job | ₹ 9,542,049 |
| J1-5''''.6 | Add capacity above 0.25 MLD to 0.50 MLD | litre | ₹ 28.28 |
| J1-5''''.7 | SEWAGE TREATMENT PLANT Designing, providing, constructing, hydraulic testing, commissioning and giving satisfactory trials of Integrated Wetland Technology (IWT) based Sewage Treatment Plant (STP) consisting of Screen chamber, Oil &Grease trap, RCC Primary treatment tanks (including manholes, vent pipes and graded gravel media) and RCC Secondary treatment tanks (SBBR) (including gravel media, PVC sheets, wetland plants, plastic mesh, etc. required.) tank, RCC intermediate and treated water tank, sludge recirculation pump and pipe network, room for tertiary treatment unit, E&M works for tertiary treatment including associated piping work, internal pathways, wire fencing, etc. complete as turnkey job with all involved civil, electrical and mechanical works inclusive of following items, units as per detailed specifications for civil, electrical and mechanical components with all duties and taxes, etc. complete as directed by Engineer-In-charge. Allied structure shall constructed as per the provision in appropriate and relevant standards and design guidelines of respective authorities. RCC and civil works will be as directed by Engineer-in-charge. Sewage Treatment Plant (STP) to designed to treat the row water sewage with the characteristics in table number "A" to produce the treated sewage with characteristics as mentioned in table number "B" A Raw Sewage Characteristics Temperature - Ambient pH - 5.5-9.0 BOD - 300 mg/L 5 COD - 600 mg/L TSS -500 mg/L Total N: 50 mg/L Total P: 15 mg/L Faecal Coliform (MPN): 10^6- 10^7 B Treated Water Characteristics Temperature - Ambient pH - 6.5-8.0 BOD < 10 mg/L 5 COD - 40 mg/L TSS < 20 mg/L Total N < 5 mg/L Total P <1 mg/L Faecal Coliform (MPN) < 10 mg/lt Note: If raw sewage characteristics observed as per test are more critical than the mentioned in description (Table A) same shall be used for the design of Sewage Treatment Plant (STP), otherwise row sewage characteristics mentioned ( Table A)shall be used. II FOLLOWING COMPONENTS ARE INCLUDED 1. SCREEN CHAMBER: Screening is a unit operation that separates large floating materials in and/or on water found in different and/or on water (found in different sizes) from water and from entering wastewater treatment facilities and mains. The unit known as a screen chamber 2. Oil and Grease Trap Designing, providing and constructing manual type Oil &Grease removal mechanism in RCC (M-300) capable removing grease, oil and scum including providing and making necessary arrangements. Removal will be done manually and stored in a tank for defined period after which it will be disposed to appropriate disposal facility. Inlet and outlet channels of required sizes as make be required to connect the flow to connecting unit, etc. complete including hydraulic testing for water tightness of structure having adequate Free Board, and platform. All arrangements shall be as detailed specifications and as directed by Engineering in Charge. 3. Primary Treatment Tank Designing, providing, constructing and hydraulic testing in RCC (M-300) watertight underground primary treatment tanks (including PSRT, SABR, BSF). Designs per the drawings given by IWT technology provider. Design will consider the average flow, the 2 DWF and the peak flow. Tank will be covered and PVC vent pipes having sand and activated carbon (as per details and design provided by technology provider) will be installed to prevent odour. 0.5% of horizontal slope is provided in the tank for the collection of sludge. Minimum free board of 0.3m is provided. It includes providing all necessary items such as gravel media, piping, valves, joints, launder, baffling, etc. as shown drawings & additional items will be as directed by Engineering in Charge. 4.Static Bed Biofilm Reactor (SBBR) Designing, providing, constructing and hydraulic testing in RCC (M-300) watertight underground secondary treatment tanks (SBBR). 0.5% of horizontal slope is provided in the tank for the collection and recirculation of sludge. Designs as per the drawings given by IWT technology provider. Design will consider the average flow, the 2 DWF and the peak flow. Wetland plants will be planted on gravel media ( as per designed by IWT technology provider). In the open recirculation sections a combination of Bottom screen, MS mesh, PVC sheet, plastic mesh will be provided to support Wetland plants. Minimum free board of 0.3m is provided. It includes providing all necessary items such as gravel media, piping, valves, joints, launder, baffling, structural steel work, bottom screens, grill work, pvc sheet, plastic mesh, wetland plants etc. as shown in drawings and additional items will be as directed by Engineering in Charge. 5. Intermediate and Treated Water Tank Designing, providing, constructing and hydraulic testing in RCC (M-300) watertight underground tank acting as feed tank for tertiary treatment avoiding backflows. Designs as per the drawings given by IWT technology provider. Design will consider the average flow, the 2 DWF and the peak flow. Tank will be covered. It includes providing all necessary items such as piping, valves, joints etc. as shown in drawings & additional items will be as directed by Engineering in Charge. 6. Tertiary Treatment Unit Designing, providing, installing and hydraulic testing of feed pump, activated carbon filter vessel with required sand and required activated carbon quantities, hypo dosing tank, dosing pump, necessary piping, pumps, joints, electrical cables, connections etc. complete. It also includes trail and run of tertiary treatment unit. After dosing contact time of 30 min allows 99.99% reduction of outstanding fecal coliform. Chlorine dosage will be as per standard requirement of 5- 10ppm. to match effluent quality as mentioned in table number "B". The Unit as per designed and approved technology provider. 7. Treated Water Outfalls Designing, providing, constructing appropriate outfall sewer of RCC NP Class -III pipe to discharge treated effluent, untreated effluent from bypass chambers to the local Nallah at the point shown on the drawing including necessary chambers for inspection and cleaning including excavation, dewatering, refilling, concrete, encasing / bedding concrete to the local Nallah at the point shown on the drawing including necessary chambers for inspection and cleaning including excavation, dewatering, refilling, concrete, encasing / bedding concrete 8. Block Diagram Integrated Wetland Technology (IWT) III PRICE SCHEDULE Capacity of the Plant in MLD Area Requirement in Sqm | job | ₹ 16,611,342 |
| J1-5''''.8 | 0.50 MLD 1100 — Add capacity above 0.5 MLD to 1 MLD | litre | ₹ 27.53 |
| J1-5''''.9 | 0.50 MLD 1100 — | job | ₹ 30,376,203 |
| J1-5''''.10 | 1.00 MLD 2090 — Add capacity above 1 MLD to 2 MLD | litre | ₹ 27.02 |
| J1-5''''.11 | 1.00 MLD 2090 — 2.00 MLD 4040 | job | ₹ 57,395,250 |
| J1-5''''.12 | 1.00 MLD 2090 — Add capacity above 2 MLD to 3 MLD | litre | ₹ 26.51 |
| J1-5''''.13 | 1.00 MLD 2090 — 3.00 MLD 5990 | job | ₹ 83,905,173 |
| J1-5''''.14 | 1.00 MLD 2090 — Add capacity above 3 MLD to 5 MLD | litre | ₹ 26.3 |
| J1-5''''.15 | 1.00 MLD 2090 — 5.00 MLD and Above 9950 NOTES | job | ₹ 136,514,884 |
| J1-5''''' | Plastic mesh and plastic tie lock | ₹ 1 | |
| J1-6'''' | PVC Sheet | ₹ 4 | |
| J1-6''''' | recirculation pumps, Power Supply Unit (PSU), Ozone Dosing System, OFF Collection & Diffusion System, associated instrumentation and control system, associated piping & valves, etc. with complete work involved electro- mechanical works inclusive of following items as per the specifications & excluding all civil work, MCC Panel, taxes & duties, etc. FOLLOWING UNITS ARE INCLUDED: | ||
| J1-6'''''.j | Ozone concentration (intermittent) Lighting, Air conditioning and Ventilation system: Ozone plant shall be erected in closed building that can be locked. Rooms where ozone might be emitted case of failure shall be effectively monitored by gas detectors with alarms that stop the generation of ozone when activated. Effective monitoring means are the gas detector sensors. Rooms with ozonation plants shall equipped with ventilation at floor level actuated automatically by the gas detectors. Ventilation shall guarantee at least three complete changes of air per hour. The bidder has to confirm and fulfill ozonisation capacities and operation of the system as adequate the following as per the guidelines of Environment problems such as supply failure, interruption in supply of ozone gas etc. Unit’s start-ups and shut downs- planned / forced. Quick stabilization of the system after any interruption. Dozing points to be selected in such a way that Ozonation is ensured for complete system. It should ensured that no ozone-depleted pockets are left out the system. The health and safety aspects are required to be elaborated so that proper precautions can be taken during operation and maintenance. Operations: On the basis of manufacturers operation & maintenance manual the supplier shall provide instruction for the operation of the ozonating plant make them accessible to all personnel who work at near the plant. Such instruction shall include the following indication: • Instruction on the operation of the parts of the plant • Starting and shut down sequence • Action in the event of the faults • Preventive measures to avoid untoward situation. Safety Signs: Safety signs marked shall be in accordance with the safety concerns at the working place. The technology design & details as per provided and approved by technology provider. Cost of Ozone Generator per kg capacity on SITC basis for High Pure Oxygen Generation System 1 | kg | ₹ 10,112,717 |
| J1-6'''''.2 | 5 | kg | ₹ 50,563,589 |
| J1-6'''''.3 | 6 | kg | ₹ 48,642,920 |
| J1-6'''''.4 | 10 | kg | ₹ 81,071,533 |
| J1-6'''''.5 | 11 | kg | ₹ 75,270,260 |
| J1-6'''''.6 | 15 | kg | ₹ 102,711,315 |
| J1-6'''''.7 | 16 | kg | ₹ 101,135,720 |
| J1-6'''''.8 | 20 NOTE 1) All kind of civil works including internal & external electrification, exhaust system, Earthing works, hoist, etc. are excluded from above scope of work. 2) MCC panel is excluded from scope of work. 3) Battery Limit for Estimation: The assembled ozone generation plant is pre-tested test field and will be delivered ready for production. The battery limits for the electric parts are the in and outlet connections on the electrical cabinet. The battery limits for the ozone dosing system are the pipeline connections of our system, at the edge of the frame. Inlet of air compressor for Oxygen Plant. | kg | ₹ 126,419,650 |
| J1-1'''' | Unit (PSU), Ozone Dosing System, Ozone Destructor, associated instrumentation and control system, associated piping & valves, etc. with complete work involved electro-mechanical works inclusive of following items as per the specifications & excluding civil work, MCC Panel, taxes & duties, etc. FOLLOWING UNITS ARE INCLUDED: | ||
| J1-1''''.j | Ozone concentration (intermittent) Lighting, Air conditioning and Ventilation system: Ozone plant shall be erected in closed building that can be locked. Rooms where ozone might be emitted case of failure shall be effectively monitored by gas detectors with alarms that stop the generation of ozone when activated. Effective monitoring means are the gas detector sensors. Rooms with ozonation plants shall equipped with ventilation at floor level actuated automatically by the gas detectors. Ventilation shall guarantee at least three complete changes of air per hour. The bidder has to confirm and fulfill ozonisation capacities and operation of the system as adequate the following as per the guidelines of Environment problems such as supply failure, interruption in supply of ozone gas etc. Unit’s start-ups and shut downs- planned / forced. Quick stabilization of the system after any interruption. Dozing points to be selected in such a way that Ozonation is ensured for complete system. It should ensured that no ozone-depleted pockets are left out the system. The health and safety aspects are required to be elaborated so that proper precautions can be taken during operation and maintenance. Operations: On the basis of manufacturers operation & maintenance manual the supplier shall provide instruction for the operation of the ozonating plant make them accessible to all personnel who work at near the plant. Such instruction shall include the following indication: • Instruction on the operation of the parts of the plant • Starting and shut down sequence • Action in the event of the faults • Preventive measures to avoid untoward situation. Safety Signs: Safety signs marked shall be in accordance with the safety concerns at the working place. The technology design & details as per provided and approved by technology provider. Cost of Ozone Generator per kg capacity on SITC basis for Disinfection 1 | kg | ₹ 8,150,918 |
| J1-1''''.2 | 5 | kg | ₹ 40,754,592 |
| J1-1''''.3 | 6 | kg | ₹ 36,340,414 |
| J1-1''''.4 | 10 | kg | ₹ 60,566,691 |
| J1-1''''.5 | 11 | kg | ₹ 60,413,851 |
| J1-1''''.6 | 15 | kg | ₹ 82,357,339 |
| J1-1''''.7 | 16 | kg | ₹ 78,947,583 |
| J1-1''''.8 | 20 NOTE 1. All kind of civil works including internal & external electrification, exhaust system, Earthing works, hoist, etc. are excluded from above scope of work. 2. MCC panel is excluded from scope of work. 3. Battery Limit for Estimation: The assembled ozone generation plant is pre-tested test field and will be delivered ready for production. The battery limits for the electric parts are the in and outlet connections on the electrical cabinet. The battery limits for the ozone dosing system are the pipeline connections of our system, at the edge of the frame. Inlet of air compressor for Oxygen Plant. b) Outlet flange of Ozone dosing system. 4. The Price mentioned under each category shall basic cost for 1 kg /hr. For the calculation of Ozone generator capacity, multiply the cost mentioned in each slab with the required capacity. e.g. If basic cost or Installation & commissioning cost of Ozone generator of range 1 - 5 kg/hr is "X" (ref row no 168) & required ozonator capacity is 3 kg/hr then the cost of that model shall be calculated as 3X. 5. All the taxes & duties are extra at actual. 6. Abbreviations: | kg | ₹ 98,684,479 |
Source: Maharashtra Jeevan Pradhikaran State Schedule of Rates 2023-24 (w.e.f. 20/06/2023), sections E to N. Rates are shown as published; check the official book and its correction slips before you submit an estimate. BESTimate is not issued by or affiliated with this department.
Need the full estimate, not just one item?
BESTimate makes the whole government-format estimate — Measurement, Abstract and Summary in Excel — with BMC, PWD, CPWD, MJP and CIDCO rates built in. Launching 26 November 2026 · first 99 to pre-register get 50% off for 6 months.
Made free with BESTimate by F K Consultant · estimate.fkconsultant.com/calculators · approximate figures — check against your drawings and local rates.