← All sections of MJP SSR 2023-24
| Code | Description | Unit | Rate |
|---|---|---|---|
| I15-1 | Providing, fabricating and fixing expansion joints for pipelines as per the drawing. The rate to include machining the strakes and steel ring as shown in the drawing and welding on either automatic welding machine or manually, Rate includes plates and flats required for expansion joint and all other materials such as synthetic rubber, rubber ring, etc. including packing as per specifications, grease, bolts and nuts, local handling, excluding GST levied by GOI & GOM in all respect etc. complete. Expansion joints suitable for pipe diameters. | ||
| I15-1.i | 300 mm | nos | ₹ 39,131 |
| I15-1.ii | 400 mm | nos | ₹ 56,470 |
| I15-1.iii | 450 mm | nos | ₹ 73,455 |
| I15-1.iv | 500 mm | nos | ₹ 98,482 |
| I15-1.v | 600 mm | nos | ₹ 115,695 |
| I15-1.vi | 700 mm | nos | ₹ 144,026 |
| I15-1.vii | 750 mm | nos | ₹ 158,716 |
| I15-1.viii | 800 mm | nos | ₹ 184,709 |
| I15-1.ix | 900 mm | nos | ₹ 214,460 |
| I15-1.x | 1000 mm | nos | ₹ 256,793 |
| I15-1.xi | 1200 mm | nos | ₹ 341,050 |
| I15-2 | Blast cleaning the surface of the old or new pipeline internally to remove all rust etc. complete, including providing copper slag/garnet, machinery, labour, cutting pipes at required places and rewelding the same etc, complete as directed by Engineer-in-charge. (Pipes pieces if required for rewelding of old pipeline shall be paid separately.) | sqm | ₹ 158 |
| I15-3 | Blast Cleaning of old or new pipeline surface internally with mechanical cleaning machine having steel scraper blades with required passes including removing all rust, scaling etc. including cutting of pipes at required places, rewelding the same including cost of all materials and labour, etc, complete (Pipes pieces if required for rewelding of old pipeline shall be paid separately.) | sqm | ₹ 158 |
| I15-4 | Blast Cleaning of old pipeline surface internally by using swabbing method by passing polyurethane foam “Pig” with required hydraulic pressure, cutting of pipes at required places, rewelding the same including cost of all materials and labour, etc. complete. (Pipe pieces if required for rewelding of old pipeline shall be paid separately.) | sqm | ₹ 186 |
| I15-5 | Blast cleaning the surface of the old or new pipeline externally to remove all rust including providing copper slag/garnet machinery etc. complete as directed by Engineer-in-charge. | sqm | ₹ 171 |
| I15-6 | Providing and applying primer and one coat of red oxide of iron paint internally to blast cleaned surface of the pipes. | sqm | ₹ 51 |
| I15-7 | Providing and applying primer and one coat of red oxide of iron paint internally including cleaning the surface of the pipes with steel scrappers, wire brushes, and metal cleaning solution, etc. | sqm | ₹ 86 |
| I15-8 | Providing and applying primer and one coat of red oxide of iron paint externally to blast cleaned surface of the pipes. | sqm | ₹ 56 |
| I15-9 | Providing and applying primer and one coat of red oxide of iron paint externally including cleaning the surface the pipes with steel scrappers, wire brushes, and metal cleaning solution, etc. | sqm | ₹ 122 |
| I15-10 | Providing and applying covering coat of grey graphite approved quality including dusting the surface etc. complete. | sqm | ₹ 63 |
| I15-11 | Providing and applying one coat of zinc rich epoxy primer to the internal surface of pipe line at site. | sqm | ₹ 133 |
| I15-12 | Providing and applying primer first coat of intertol 49 emaline 05/58 pipe coat or any other equivalent approved paint to the internal surface of pipe line at site. | ||
| I15-12.1 | Providing and applying primer first coat of intertol 49 emaline 05/58 pipe coat or any other equivalent approved paint to the internal surface of pipe line at site. | sqm | ₹ 102 |
| I15-12.b | Second coat | sqm | ₹ 83 |
| I15-12.c | Third coat | sqm | ₹ 81 |
Source: Maharashtra Jeevan Pradhikaran State Schedule of Rates 2023-24 (w.e.f. 20/06/2023), sections E to N. Rates are shown as published; check the official book and its correction slips before you submit an estimate. BESTimate is not issued by or affiliated with this department.
Need the full estimate, not just one item?
BESTimate makes the whole government-format estimate — Measurement, Abstract and Summary in Excel — with BMC, PWD, CPWD, MJP and CIDCO rates built in. Launching 26 November 2026 · first 99 to pre-register get 50% off for 6 months.
Made free with BESTimate by F K Consultant · estimate.fkconsultant.com/calculators · approximate figures — check against your drawings and local rates.