Free civil calculators

Stone Work

CPWD DSR 2023 · section 7

53 items of section 7 (Stone Work) of the CPWD DSR 2023 — code, description, unit and rate. Units: cum, nos, rmt, sqm.

← All sections of CPWD DSR 2023

CodeDescriptionUnitRate
7.1Random rubble masonry with hard stone in foundation and plinth including levelling up with cement concrete 1:6:12 (1 cement: 6 coarse sand: 12 graded stone aggregate 20 mm nominal size) upto plinth level with:
7.1.1Cement mortar 1:6 (1 cement: 6 coarse sand)cum₹ 7,311.25
7.2Random rubble masonry with hard stone in superstructure above plinth level and upto floor five level, including leveling up with cement concrete 1:6:12 (1 cement: 6 coarse sand: 12 graded stone aggregate 20 mm nominal size) at window sills, ceiling level and the like.
7.2.1Cement mortar 1:6 (1 cement: 6 coarse sand)cum₹ 9,275.45
7.4Extra for random rubble masonry with hard stone in:
7.4.1Square or rectangular pillarscum₹ 956
7.4.2Circular pillarscum₹ 2,530.6
7.5Extra for random rubble masonry with hard stone curved on plan for a mean radius not exceeding 6 m.cum₹ 1,046.2
7.6Coursed rubble masonry (first sort) with hard stone in foundation and plinth with:
7.6.1Cement mortar 1:6 (1 cement: 6 coarse sand)cum₹ 8,812.05
7.7Coursed rubble masonry (second sort) with hard stone in foundation & plinth with:
7.7.1Cement mortar 1:6 (1 cement: 6 coarse sand)cum₹ 8,198.55
7.8Coursed rubble masonry with hard stone (first or second sort) in superstructure above plinth level and upto floor five level.
7.8.1Masonry work (first sort), in cement mortar 1:6 (1 cement: 6 coarse sand)cum₹ 10,741.6
7.8.2Masonry work (second sort), in cement mortar 1:6 (1 cement: 6 coarse sand)cum₹ 10,128.1
7.10Extra for coursed rubble masonry with hard stone (first or second sort) in:
7.10.1Square or rectangular pillarscum₹ 1,060.5
7.10.2Circular pillarscum₹ 2,874.2
7.11Extra for coursed rubble masonry with hard stone (first or second sort) curved on plan for a mean radius not exceeding 6 m.cum₹ 1,133.65
7.12.1Stone work in plain ashlar in super structure upto floor five level in cement mortar 1:6 (1 cement: 6 coarse sand) including pointing with cement mortar 1:2 (1 white cement: 2 stone dust) with an admixture of pigment matching the stone shade: — Stone work in plain ashlar in super structure upto floor five level in cement mortar 1:6 (1 cement: 6 coarse sand) including pointing with cement mortar 1:2 (1 white cement: 2 stone dust) with an admixture of pigment matching the stone shade: — One face dressed
7.12.1.1Red sand stonecum₹ 68,294
7.12.1.2White sand stonecum₹ 82,518
7.12.2Stone work in plain ashlar in super structure upto floor five level in cement mortar 1:6 (1 cement: 6 coarse sand) including pointing with cement mortar 1:2 (1 white cement: 2 stone dust) with an admixture of pigment matching the stone shade: — Stone work in plain ashlar in super structure upto floor five level in cement mortar 1:6 (1 cement: 6 coarse sand) including pointing with cement mortar 1:2 (1 white cement: 2 stone dust) with an admixture of pigment matching the stone shade: — Both face dressed
7.12.2.1Red sand stonecum₹ 91,295
7.12.2.2White sand stonecum₹ 105,519
7.13.1Stone work plain ashlar in arches in super structure upto floor V level in cement mortar 1:3 (1 cement: 3 coarse sand) including centering, shuttering and pointing with white cement mortar 1:2 (1 white cement: 2 stone dust) with an admixture of pigment matching the stone shade. — Stone work plain ashlar in arches in super structure upto floor V level in cement mortar 1:3 (1 cement: 3 coarse sand) including centering, shuttering and pointing with white cement mortar 1:2 (1 white cement: 2 stone dust) with an admixture of pigment matching the stone shade. — One face dressed
7.13.1.1Red sand stonecum₹ 75,263
7.13.1.2White sand stonecum₹ 89,487
7.13.2Stone work plain ashlar in arches in super structure upto floor V level in cement mortar 1:3 (1 cement: 3 coarse sand) including centering, shuttering and pointing with white cement mortar 1:2 (1 white cement: 2 stone dust) with an admixture of pigment matching the stone shade. — Stone work plain ashlar in arches in super structure upto floor V level in cement mortar 1:3 (1 cement: 3 coarse sand) including centering, shuttering and pointing with white cement mortar 1:2 (1 white cement: 2 stone dust) with an admixture of pigment matching the stone shade. — Both face dressed
7.13.2.1Red sand stonecum₹ 98,265
7.13.2.2White sand stonecum₹ 112,488
7.14.1Stone work plain ashlar in domes, in super structure upto floor V level in cement mortar 1:3 (1 cement: 3 coarse sand) including centering, shuttering and pointing with white cement mortar 1:2 (1 white cement: 2 stone dust) with an admixture of pigment matching the stone shade. — Stone work plain ashlar in domes, in super structure upto floor V level in cement mortar 1:3 (1 cement: 3 coarse sand) including centering, shuttering and pointing with white cement mortar 1:2 (1 white cement: 2 stone dust) with an admixture of pigment matching the stone shade. — One face dressed
7.14.1.1Red sand stonecum₹ 114,277
7.14.1.2White sand stonecum₹ 128,500
7.14.2Stone work plain ashlar in domes, in super structure upto floor V level in cement mortar 1:3 (1 cement: 3 coarse sand) including centering, shuttering and pointing with white cement mortar 1:2 (1 white cement: 2 stone dust) with an admixture of pigment matching the stone shade. — Stone work plain ashlar in domes, in super structure upto floor V level in cement mortar 1:3 (1 cement: 3 coarse sand) including centering, shuttering and pointing with white cement mortar 1:2 (1 white cement: 2 stone dust) with an admixture of pigment matching the stone shade. — Both face dressed
7.14.2.1Red sand stonecum₹ 169,953
7.14.2.2White sand stonecum₹ 184,177
7.15.1Stone work ashlar punched (ordinary) in superstructure upto floor five level in cement mortar 1:6 (1 white cement: 6 coarse sand) including pointing with white cement mortar 1:2 (1 white cement: 2 stone dust) with an admixture of pigment matching the stone shade. — Stone work ashlar punched (ordinary) in superstructure upto floor five level in cement mortar 1:6 (1 white cement: 6 coarse sand) including pointing with white cement mortar 1:2 (1 white cement: 2 stone dust) with an admixture of pigment matching the stone shade. — One face dressed
7.15.1.1Red sand stonecum₹ 64,926
7.15.1.2White sand stonecum₹ 79,150
7.15.2Stone work ashlar punched (ordinary) in superstructure upto floor five level in cement mortar 1:6 (1 white cement: 6 coarse sand) including pointing with white cement mortar 1:2 (1 white cement: 2 stone dust) with an admixture of pigment matching the stone shade. — Stone work ashlar punched (ordinary) in superstructure upto floor five level in cement mortar 1:6 (1 white cement: 6 coarse sand) including pointing with white cement mortar 1:2 (1 white cement: 2 stone dust) with an admixture of pigment matching the stone shade. — Both faced punched
7.15.2.1Red sand stonecum₹ 84,560
7.15.2.2White sand stonecum₹ 98,784
7.16Extra for stone work, random rubble / coursed rubble masonry / ashlar masonry above floor V level for every four floors or part thereof by mechnical means.cum₹ 169.45
7.17Extra for plain ashlar or ashlar punched in:
7.17.1Square or rectangular pillarscum₹ 2,896
7.18Extra for stone work; plain ashlar or ashlar punched curved on plan with a mean radius not exceeding 6 m.cum₹ 2,014
7.19Extra for additional cost of centering for arches exceeding 6m span including all strutting, bolting, wedging etc. and removal (area of soffit to be measured).sqm₹ 608.15
7.20Stone work ashlar sunk or moulded or sunk and moulded upto floor five level in cement mortar 1:6 (1 cement: 6 coarse sand) including pointing with white cement mortar 1:2 (1 white cement: 2 stone dust) with an admixture of pigment matching the stone shade:
7.20.1Red sand stonecum₹ 94,463
7.20.2White sand stonecum₹ 108,686
7.21Extra for stone work ashlar sunk or moulded or sunk and moulded or carved in:
7.21.1Triangular or Square or rectangular pillarscum₹ 3,779
7.21.2Circular or polygonal pillarscum₹ 10,706
7.22Extra for stone work ashlar sunk or moulded in cornices.rmt₹ 303.5
7.24Extra for stone work (veneer work) curved on plan with a mean radius not exceeding 6 m.cum₹ 2,896
7.26Providing and fixing stone dowels 10x5x2.50 cm cut to double wedge shape as per design in cement mortar 1:2 (1 cement: 2 coarse sand), including making the necessary chases.nos₹ 54.55
7.28.1Providing and fixing sloping chajja of stone 40 mm thick and upto 80 cm wide beyond the wall as measured along the slope in cement mortar 1:4 (1 cement: 4 coarse sand) with 12 mm diameter anchoring steel bar, 45 cm long, fixed in each stone and supported on and including with bricks cove in cement mortar 1:4 (1 cement: 4 coarse sand), including pointing in cement mortar 1:2 (1 white cement: 2 stone dust) with an admixture of pigment matching the stone shade: — Red sand stone:
7.28.1.1With common burnt clay F.P.S.(non modular) bricks of class designation 7.5sqm₹ 2,854.35
7.28.2Providing and fixing sloping chajja of stone 40 mm thick and upto 80 cm wide beyond the wall as measured along the slope in cement mortar 1:4 (1 cement: 4 coarse sand) with 12 mm diameter anchoring steel bar, 45 cm long, fixed in each stone and supported on and including with bricks cove in cement mortar 1:4 (1 cement: 4 coarse sand), including pointing in cement mortar 1:2 (1 white cement: 2 stone dust) with an admixture of pigment matching the stone shade: — White sand stone:
7.28.2.1With common burnt clay F.P.S.(non modular) bricks of class designation 7.5sqm₹ 2,932.6
7.29Providing and fixing horizontal chajja of stone 40 mm thick and upto 80 cm projection in cement mortar 1:4 (1 cement: 4 coarse sand), including pointing in white cement mortar 1:2 (1 white cement: 2 stone dust) with an admixture of pigment matching the stone shade:
7.29.1Red sand stonesqm₹ 1,833.25
7.29.2White sand stonesqm₹ 1,901.55
7.3030 mm red sand stone sun-shade (chisel-dressed) supported on red sand stone brackets, fixed in walls with cement mortar 1:4 (1 cement: 4 coarse sand), including finishing complete.sqm₹ 2,159.9
7.31Providing and fixing red sand stone brackets 55x22.5x45 cm sunk and moulded including providing and fixing with 4 Nos gun metal cramp 25x6 mm 30 cm longnos₹ 6,788.85
7.32Stone work, plain in copings, cornices, string courses and plinth courses, upto 75 mm thick in Cement mortar 1:6 (1 cement: 6 coarse sand), including pointing with white cement mortar 1:2 (1 white cement: 2 stone dust) with an admixture of pigment matching the stone shade.
7.32.1Red sand stonecum₹ 93,741.1
7.32.2White sand stonecum₹ 107,965.1
7.33Providing and fixing stone jali 40 mm thick throughout in cement mortar 1:3 (1 cement: 3 coarse sand), including pointing in white cement mortar 1:2 (1 white cement: 2 stone dust) with an admixture of pigment, matching the stone shade, jali slab without any chamfers etc.
7.33.1Red sand stonesqm₹ 14,931.55
7.33.2White sand stonesqm₹ 14,994.15
7.34Extra for laying stone work in or under water and/or liquid mud including cost of pumping or bailing out water and removing slush etc. complete. NOTE:- The quantity will be calculated by multiplying the depth measured from sub-soil water level up to the centre of gravity of stone work under sub - water with the quantity of stone work in cum executed under the sub-soil water. The depth of centre of gravity shall be reckoned correct to 0.1 m, (0.05 m or more shall be taken as 0.1 m and less than 0.05 m ignored).cum₹ 1,098.8
7.35Extra for laying stone work in or under foul condition.cum₹ 467.55
7.38.1Stone tile work for wall lining upto 10 m height with special adhesive over 12 mm thick bed of cement mortar 1:3 (1 cement: 3 coarse sand), including pointing in white cement with an admixture of pigment to match the stone shade. — Stone tile work for wall lining upto 10 m height with special adhesive over 12 mm thick bed of cement mortar 1:3 (1 cement: 3 coarse sand), including pointing in white cement with an admixture of pigment to match the stone shade. — 8 mm thick (mirror polished and machine cut edge)
7.38.1.1Granite stone of any colour and shadesqm₹ 3,094.55
7.38.1.2Raj Nagar plain white marble/ Udaipur green marble/ Zebra black marblesqm₹ 2,766.45
Make the estimate with these rates. BESTimate fills the description, unit and rate when you pick the item code — Measurement, Abstract and Summary in Excel.Try BESTimate →

Source: Delhi Schedule of Rates 2023 (Vol. 1 & 2), Central Public Works Department — Delhi market rates as on 01.04.2023; apply the cost index for your place and date. Rates are shown as published; check the official book and its correction slips before you submit an estimate. BESTimate is not issued by or affiliated with this department.

Need the full estimate, not just one item?

BESTimate makes the whole government-format estimate — Measurement, Abstract and Summary in Excel — with BMC, PWD, CPWD, MJP and CIDCO rates built in. Launching 26 November 2026 · first 99 to pre-register get 50% off for 6 months.

Pre-register free →

Made free with BESTimate by F K Consultant · estimate.fkconsultant.com/calculators · approximate figures — check against your drawings and local rates.